STS-126 Countdown Timeline COMPILED BY WILLIAM HARWOOD Updated: November 11, 2008
Changes and additions: As always, all countdown events prior to the end of the T-minus nine-minute hold are targeted to the opening of the shuttle's launch window. For station flights, the shuttle must take off within five minutes or so of the moment Earth's rotation carries the launch pad into the plane of the station's orbit. NASA targets the middle of that window for launch. Please note that NASA rounds down, not up, for countdown calculations. The release of the final hold at T-minus nine-minutes is targeted to the actual launch time (times in EST).
NOTE: The following countdown is an extrapolation based on hold times in NASA's initial summary timeline. The timing of some events may change when a detailed countdown timeline is generated. Updates will be posted as warranted.
EST...........EVENT 11/11/08 09:30 PM......Call to stations 10:00 PM......Countdown begins Wed 11/12/08 08:00 AM......Fuel cell reactant load preps 01:30 PM......MEC/SRB power up 02:00 PM......Clear crew module 02:00 PM......Begin 4-hour built-in hold 02:00 PM......Clear blast danger area 02:45 PM......Orbiter pyro-initiator controller test 02:55 PM......SRB PIC test 03:55 PM......Master events controller pre-flight BITE test 06:00 PM......Resume countdown 07:30 PM......Fuel cell oxygen loading begins 10:00 PM......Fuel cell oxygen load complete 10:00 PM......Fuel cell hydrogen loading begins 10:30 PM......Fuel cell hydrogen loading complete Thu 11/13/08 01:30 AM......Pad open; ingress white room 02:00 AM......Begin 4-hour built-in hold 02:00 AM......Crew module clean and vacuum 02:30 AM......OMBUU demate 04:00 AM......Secure MLP interior 06:00 AM......Countdown resumes 06:00 AM......Main engine preps 06:00 AM......MECs 1 and 2 on; avionics system checkout 07:00 AM......Remove OMS engine covers, throat plugs 07:30 AM......Deflate RSS dock seals; tile inspection 08:00 AM......Tile inspection 12:00 PM......TSM prepped for fueling 02:07 PM......Begin 13-hour 30-minute hold 03:45 PM......Crew weather briefing 04:30 PM......OIS communications check 05:20 PM......JSC flight control team on station 06:30 PM......Comm activation 07:00 PM......Crew module voice checks 08:00 PM......Flight crew equipment late stow 08:30 PM......Debris inspection 11:30 PM......RSS to park position Fri 11/14/08 12:30 AM......Final TPS, debris inspection 01:30 AM......Ascent switch list 03:00 AM......Crew sleep begins 03:30 AM......Resume countdown 03:30 AM......ASP cockpit config 03:50 AM......Pad clear of non-essential personnel 03:50 AM......APU bite test 04:40 AM......Fuel cell activation 05:30 AM......Booster joint heater activation 06:00 AM......MEC pre-flight bite test 06:15 AM......Tanking weather update 07:00 AM......Final fueling preps; launch area clear 07:30 AM......Red crew assembled 08:15 AM......Fuel cell integrity checks complete 08:30 AM......Begin 2-hour built-in hold (T-minus 6 hours) 08:40 AM......Safe-and-arm PIC test 09:23 AM......Crew wakeup 09:30 AM......External tank ready for loading 09:45 AM......Mission management team tanking meeting 10:30 AM......Resume countdown (T-minus 6 hours) 10:30 AM......LO2, LH2 transfer line chilldown 10:40 AM......Main propulsion system chill down 10:40 AM......LH2 slow fill 11:00 AM......Crew wakeup 11:10 AM......LO2 slow fill 11:15 AM......Hydrogen ECO sensors go wet 11:20 AM......LO2 fast fill 11:30 AM......LH2 fast fill 01:25 PM......LH2 topping 01:30 PM......LH2 replenish 01:30 PM......LO2 replenish 01:30 PM......Begin 2-hour 30-minute built-in hold (T-minus 3 hours) 01:30 PM......Closeout crew to white room 01:30 PM......External tank in stable replenish mode 01:45 PM......Astronaut support personnel comm checks 02:15 PM......Pre-ingress switch reconfig 02:30 PM......NASA TV coverage begins 02:33 PM......Crew breakfast/photo op (recorded) 03:25 PM......Final crew weather briefing 03:35 PM......Crew suit up begins 04:00 PM......Resume countdown (T-minus 3 hours) 04:05 PM......Crew departs O&C building 04:35 PM......Crew ingress 05:25 PM......Astronaut comm checks 05:40 PM......Hatch closure 06:20 PM......White room closeout 06:40 PM......Begin 10-minute built-in hold (T-minus 20m) 06:50 PM......NASA test director countdown briefing 06:50 PM......Resume countdown (T-minus 20m) 06:51 PM......Backup flight computer to OPS 1 06:55 PM......KSC area clear to launch 07:01 PM......Begin final built-in hold (T-minus 9m) 07:31 PM......NTD launch status verification 07:46:34 PM...Resume countdown (T-minus 9m) 07:48:04 PM...Orbiter access arm retraction 07:50:34 PM...Launch window opens 07:50:34 PM...Hydraulic power system (APU) start 07:50:39 PM...Terminate LO2 replenish 07:51:34 PM...Purge sequence 4 hydraulic test 07:51:34 PM...IMUs to inertial 07:51:39 PM...Aerosurface profile 07:52:04 PM...Main engine steering test 07:52:39 PM...LO2 tank pressurization 07:52:59 PM...Fuel cells to internal reactants 07:53:04 PM...Clear caution-and-warning memory 07:53:34 PM...Crew closes visors 07:53:37 PM...LH2 tank pressurization 07:54:44 PM...SRB joint heater deactivation 07:55:03 PM...Shuttle GPCs take control of countdown 07:55:13 PM...SRB steering test 07:55:27 PM...Main engine start (T-6.6 seconds) 07:55:34 PM...SRB ignition (LAUNCH) |
||||