STS-131 Countdown Timeline COMPILED BY WILLIAM HARWOOD Updated: April 1, 2010
Editor's Note: The launch window is roughly 10 minutes long. To maximize ascent performance, NASA targets the middle of the window. A final hold in the countdown at the T-minus nine-minute mark will be extended as required to hit the desired launch time.
EDT...........EVENT Fri 04/02/10 02:30 AM......Call to stations 03:00 AM......Countdown begins 12:00 PM......Crew sleep begins 01:00 PM......Fuel cell reactant load preps 06:30 PM......MEC/SRB power up 07:00 PM......Clear crew module 07:00 PM......Begin 4-hour built-in hold 07:00 PM......Clear blast danger area 07:45 PM......Orbiter pyro-initiator controller test 07:55 PM......SRB PIC test 08:00 PM......Crew wakeup 08:55 PM......Master events controller pre-flight BITE test 11:00 PM......Resume countdown Sat 04/03/10 12:30 AM......Fuel cell oxygen loading begins 03:00 AM......Fuel cell oxygen load complete 03:00 AM......Fuel cell hydrogen loading begins 05:30 AM......Fuel cell hydrogen loading complete 06:30 AM......Pad open; ingress white room 07:00 AM......Begin 9-hour built-in hold 07:00 AM......PRSD offload 09:00 AM......Crew module clean and vacuum 12:00 PM......Crew sleep begins 12:30 PM......OMBUU demate 01:00 PM......Remove APU vent covers 01:30 PM......MPS 2000 psi GSE 04:00 PM......Countdown resumes 04:00 PM......Main engine preps 04:00 PM......MECs 1 and 2 on; avionics system checkout 06:00 PM......FRCS Tyvek cover remova/inspect 08:00 PM......Crew wakeup 10:30 PM......Deflate RSS dock seals; tile inspection 11:00 PM......Tile inspection 11:00 PM......TSM prepped for fueling Sun 04/04/10 12:00 AM......Begin 13-hour 56-minute hold 12:00 AM......L-1 engineering briefing 12:15 AM......Crew weather briefing 12:30 AM......Crew orbiter/payload briefings 01:00 AM......NASA TV coverage of Soyuz TMA-18 docking 01:28 AM......Soyuz TMA-18 docking with ISS 01:30 AM......ASP crew module inspection 01:30 AM......OIS communications check 03:20 AM......JSC flight control team on station 03:30 AM......Comm activation 04:00 AM......Crew module voice checks 04:30 AM......Soyuz TMA-18/ISS hatch opening 05:00 AM......Flight crew equipment late stow 09:30 AM......RSS to park position 10:30 AM......Final TPS, debris inspection 11:00 AM......Ascent switch list 12:00 PM......Crew sleep begins 01:56 PM......Resume countdown 02:16 PM......Pad clear of non-essential personnel 02:16 PM......APU bite test 03:06 PM......Fuel cell activation 03:56 PM......Booster joint heater activation 04:26 PM......MEC pre-flight bite test 04:41 PM......Tanking weather update 05:26 PM......Final fueling preps; launch area clear 05:56 PM......Red crew assembled 06:41 PM......Fuel cell integrity checks complete 06:56 PM......Begin 2-hour built-in hold (T-minus 6 hours) 07:06 PM......Safe-and-arm PIC test 07:56 PM......External tank ready for loading 08:00 PM......Crew wakeup 08:19 PM......Mission management team tanking meeting 08:45 PM......NASA TV fueling coverage begins 08:56 PM......Resume countdown (T-minus 6 hours) 08:56 PM......LO2, LH2 transfer line chilldown 09:00 PM......Final crew medical checks 09:06 PM......Main propulsion system chill down 09:06 PM......LH2 slow fill 09:36 PM......LO2 slow fill 09:41 PM......Hydrogen ECO sensors go wet 09:46 PM......LO2 fast fill 09:49 PM......Crew medical checks 09:56 PM......LH2 fast fill 11:51 PM......LH2 topping 11:56 PM......LH2 replenish 11:56 PM......LO2 replenish 11:56 PM......Begin 2-hour 30-minute built-in hold (T-minus 3 hours) 11:56 PM......Closeout crew to white room 11:56 PM......External tank in stable replenish mode Mon 04/05/10 12:11 AM......Astronaut support personnel comm checks 12:41 AM......Pre-ingress switch reconfig 01:15 AM......NASA TV launch coverage begins 01:56 AM......Final crew weather briefing 02:01 AM......Crew suit up begins 02:26 AM......Resume countdown (T-minus 3 hours) 02:31 AM......Crew departs O&C building 03:01 AM......Crew ingress 03:51 AM......Astronaut comm checks 04:16 AM......Hatch closure 04:46 AM......White room closeout 05:06 AM......Begin 10-minute built-in hold (T-minus 20m) 05:16 AM......NASA test director countdown briefing 05:16 AM......Resume countdown (T-minus 20m) 05:17 AM......Backup flight computer to OPS 1 05:21 AM......KSC area clear to launch 05:27 AM......Begin final built-in hold (T-minus 9m) 05:57:23 AM...NTD launch status verification 06:12:23 AM...Resume countdown (T-minus 9m) 06:16:23 AM...Orbiter access arm retraction 06:16:23 AM...Launch window opens 06:16:23 AM...Hydraulic power system (APU) start 06:16:28 AM...Terminate LO2 replenish 06:17:23 AM...Purge sequence 4 hydraulic test 06:17:23 AM...IMUs to inertial 06:17:28 AM...Aerosurface profile 06:17:53 AM...Main engine steering test 06:18:28 AM...LO2 tank pressurization 06:18:48 AM...Fuel cells to internal reactants 06:18:53 AM...Clear caution-and-warning memory 06:19:23 AM...Crew closes visors 06:19:26 AM...LH2 tank pressurization 06:20:33 AM...SRB joint heater deactivation 06:20:52 AM...Shuttle GPCs take control of countdown 06:21:02 AM...SRB steering test 06:21:16 AM...Main engine start (T-6.6 seconds) 06:21:23 AM...SRB ignition (LAUNCH) |
||||||||||||||||||||
|
INDEX | PLUS | NEWS ARCHIVE | LAUNCH SCHEDULE ASTRONOMY NOW | STORE ADVERTISE © 2012 Spaceflight Now Inc. |
||||||||||||||||||||||