STS-129 Countdown Timeline COMPILED BY WILLIAM HARWOOD Updated: September 21, 2009
Changes and additions: Editor's Note: The launch window is roughly 10 minutes long. To maximize ascent performance, NASA targets the middle of the window. A final hold in the countdown at the T-minus nine-minute mark will be extended as required to hit the desired launch time.
The following countdown only covers the day of launch. A detailed countdown will be posted here as soon as it is available.
EST...........EVENT Thu 11/12/09 12:05 AM......Pad clear of non-essential personnel 12:05 AM......APU bite test 12:55 AM......Fuel cell activation 01:45 AM......Booster joint heater activation 02:15 AM......MEC pre-flight bite test 02:30 AM......Tanking weather update 03:15 AM......Final fueling preps; launch area clear 03:45 AM......Red crew assembled 04:30 AM......Fuel cell integrity checks complete 04:45 AM......Begin 2-hour built-in hold (T-minus 6 hours) 04:55 AM......Safe-and-arm PIC test 05:45 AM......External tank ready for loading 06:08 AM......Mission management team tanking meeting 06:45 AM......Resume countdown (T-minus 6 hours) 06:45 AM......LO2, LH2 transfer line chilldown 06:55 AM......Main propulsion system chill down 06:55 AM......LH2 slow fill 07:25 AM......LO2 slow fill 07:30 AM......Hydrogen ECO sensors go wet 07:35 AM......LO2 fast fill 07:38 AM......Crew medical checks 07:45 AM......LH2 fast fill 09:40 AM......LH2 topping 09:45 AM......LH2 replenish 09:45 AM......LO2 replenish 09:45 AM......Begin 2-hour 30-minute built-in hold (T-minus 3 hours) 09:45 AM......Closeout crew to white room 09:45 AM......External tank in stable replenish mode 10:00 AM......Astronaut support personnel comm checks 10:30 AM......Pre-ingress switch reconfig 11:00 AM......NASA TV coverage begins 11:45 AM......Final crew weather briefing 11:50 AM......Crew suit up begins 12:15 PM......Resume countdown (T-minus 3 hours) 12:20 PM......Crew departs O&C building 12:50 PM......Crew ingress 01:40 PM......Astronaut comm checks 02:05 PM......Hatch closure 02:35 PM......White room closeout 02:55 PM......Begin 10-minute built-in hold (T-minus 20m) 03:05 PM......NASA test director countdown briefing 03:05 PM......Resume countdown (T-minus 20m) 03:06 PM......Backup flight computer to OPS 1 03:10 PM......KSC area clear to launch 03:16 PM......Begin final built-in hold (T-minus 9m) 03:46:25 PM...NTD launch status verification 04:01:25 PM...Resume countdown (T-minus 9m) 04:05:25 PM...Orbiter access arm retraction 04:05:25 PM...Launch window opens 04:05:25 PM...Hydraulic power system (APU) start 04:05:30 PM...Terminate LO2 replenish 04:06:25 PM...Purge sequence 4 hydraulic test 04:06:25 PM...IMUs to inertial 04:06:30 PM...Aerosurface profile 04:06:55 PM...Main engine steering test 04:07:30 PM...LO2 tank pressurization 04:07:50 PM...Fuel cells to internal reactants 04:07:55 PM...Clear caution-and-warning memory 04:08:25 PM...Crew closes visors 04:08:28 PM...LH2 tank pressurization 04:09:35 PM...SRB joint heater deactivation 04:09:54 PM...Shuttle GPCs take control of countdown 04:10:04 PM...SRB steering test 04:10:18 PM...Main engine start (T-6.6 seconds) 04:10:25 PM...SRB ignition (LAUNCH) |
||||||||||||||||||||
|
INDEX | PLUS | NEWS ARCHIVE | LAUNCH SCHEDULE ASTRONOMY NOW | STORE ADVERTISE © 2012 Spaceflight Now Inc. |
||||||||||||||||||||||